【实用资料】一份实用甲板部坞修检查清单分享

A. Preparation for Dry-Dock

1. Marking of reparing places. 

2. Check of necessary spares and stores during dry-dock. And if not sufficient, preparation of receiving them. 

3. Plan for entering draft and deballasting.

4. Confirming the way of discharging water/oil from inspecting tank.

and opening of manholes of inspecting tank. 

5. Preliminary performance test for each eqipments. 

6. Preparation of tables for bottom plugs' position a.nd R.O.B. in each tanks. 

7. Carry out holds cleaning after confirm with the Company. 

8. Prevention measures of discharging water during dry-dock. 

9. Disposal of garbages. 

10. Preparation of lock for cabins and stores. Storage of the valuables. 

11. Storage of nuts for opening manholes and replace poor condition of them. 

12. Preparation of check list for opened manholes. 

13. Discharging of holds bildge. 

14. Taking photo as evidence before applying paint for life boats and others. 

15. Arrangement to hold bilge wells against sand blast work. 

16. Ensuring of drinking and fresh water, and plan of its using and disposal. (if living on board during dry-docking). 

17. Marking of tools (for prevention of theif, preferable attractive color). 

18. Collection of navigation information until dockyard and special regulation.

at place of dockyard, and the information shall be provided to the crew. 

19. Table of arrangement for each sensors on bottom. 

B. Works with dry-docking in

1. Re-confirming of draft, anchorage, time of entering dock and others. 

2. Closing of toilets.

3. Closing of overboard valve for sewage plant.

4. Transfering galley to shore.

5. Confirming of lock up for cabins and stores.

6. Storage of each sensors on bottom and power off.

7. Stop of operation for navigation appliance and cargo gears.

C. Works with dry-docking out

1. Confirming of time of dry-docking out and the information shall be provided to crew.

2. Preparation of sailing documents.

3. Confirming of painted condition for out of hull including bottom.

4. Confirming of removal of steps in tanks/holds, and cargo residue in bildge well.

5. Unloading of exchanged useless parts and hydraulic oil.

6. Confirming of closing for bottom plugs and fitting for sea-chest grid cover.

7. Confirming of closing for manholes of tanks.

8. Confirming of draft for dry-docking out and preparation of ballasting plan.

9. Measuring of ship's constant.

10. Opening of overboard valve for sewage plant.

11. Opening of toilets.

12. Confirming of re-fitted each sensors on bottom.

13. Confirming of operation for navigation appliance and cargo gear.

14. Inform to concerned parties after return to original couse.

15. Preparation for statement of deviation.

本站仅提供存储服务,所有内容均由用户发布,如发现有害或侵权内容,请点击举报
打开APP,阅读全文并永久保存 查看更多类似文章
猜你喜欢
类似文章
【热】打开小程序,算一算2024你的财运
We should be a "storage battery" while learning
GMP英语翻译
Fitting section Battery project--Lithium-ion Battery 3
悟 Inspire 1 - 智能飞行电池安全使用指引 1.4
大型浮顶罐抗风研究现状与分析
基于Yolo-V3对卫星图像进行储油罐容积占用率的研究
更多类似文章 >>
生活服务
热点新闻
分享 收藏 导长图 关注 下载文章
绑定账号成功
后续可登录账号畅享VIP特权!
如果VIP功能使用有故障,
可点击这里联系客服!

联系客服