Standardized Work Introduction-04

4.0  Takt Time Calculation    节拍时间计算

Takt Time is the rate of production, in seconds per piece,needed to meet customer demand.

         Takt =Seconds per week worked / Customer demand per week

节拍时间是满足客户需求所需的生产率(单位=秒)

节拍=每周工作秒数/客户每周需求数量

·     Takt Time iscalculated from:                  节拍时间计算依据

1.    Available seconds per day toproduce it    每天可用来生产的时间秒数

2.    Customer demand per day                    客户每天需求数量

4.1  Determining the Normal Factory Work Hours   正常工作时间

Determine how many shifts the production area is runningper day (under normal working conditions). Subtract any normally plannedcontractual time, such as breaks and lunches, when the area would not berunning.  This is the “Available Time.”  Convert into seconds.

确定生产区域每天运行多少个班次(正常工作条件下),减去正常的作息时间,例如休息和午饭.这是“可用时间”并转换为秒

4.2  Takt Time Calculation             节拍时间计算

Now figure the customer demand for this area.   Once you know the customer demand, you areready to calculate Takt!  Divide the Availabletime in Sec by the Customer demand

现在计算该区域的客户需求。当你知道了客户需求,你已经准备计算节拍!

用可用时间除以客户需求.

                           

4.3  Takt Time calculation: example    节拍时间计算

Working 1 shift per day  每天运行1个班/8小时

480 min shift – 54min breaks & lunch(休息&吃饭) = 426 min availabletime  (可用时间)

426 min per day X 60sec/ min = 25,560 sec /day  (每天可用时间/秒)

Weekly demand is10,000 pcs / wk   每周客户需求数量:10,000

Daily demand is 10000pcs/wk  ÷ 5 days/wk = 2,000 pcs /day每天2,000个

Takt = 25.560 sec/pc  ÷ 2000 pcs/day = 13 sec/pc

节拍=每天可用时间/每天客户需求数量=13秒/个

本站仅提供存储服务,所有内容均由用户发布,如发现有害或侵权内容,请点击举报
打开APP,阅读全文并永久保存 查看更多类似文章
猜你喜欢
类似文章
【精益生产英文】谈谈TAKT time(节拍时间)
Takt time ,Cycle time 和Lead Time的区别和联系
TT、CT、ATT、LT,能分清吗
精益生产中JIT的概念怎么理解?
亚马逊全球标准化守则(6 )-每一个流程都应该有一个节奏或节拍时间,节拍时间应该是基于处理一个标准的,没有问题工作单元所需求时间
流水线平衡
更多类似文章 >>
生活服务
热点新闻
分享 收藏 导长图 关注 下载文章
绑定账号成功
后续可登录账号畅享VIP特权!
如果VIP功能使用有故障,
可点击这里联系客服!

联系客服